With more than a little controversy, the Oklahoma City Council has approved a timeline for all the MAPS 3 projects. Included in this timeline for the 57 miles of new bicycle trails included in the MAPS projects:

Trails

• Fifty-seven miles of trails for walking, cycling and other outdoor activities are planned. The locations of the trails are still being worked out, but they expect to make use of lakes and other well-used areas of the city. They will be built in three phases beginning in 2013.

• Estimated cost: $40 million

• Planned completion date: Late 2017